Question: Which applies when using the critical ratio (CR) to schedule work? a) A CR of more than 1.0 means that the job has some slack.

Which applies when using the critical ratio (CR) to schedule work?

a) A CR of more than 1.0 means that the job has some slack.

b) A job with a CR of 1.0 should be given highest priority.

c) A job with a CR of 2.0 should be scheduled first.

d) We first schedule the job with the highest CR.

Step by Step Solution

3.50 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a A CR of m... View full answer