Question: Which method for project management removes safety times from task estimates in the planning stage? a) Program evaluation and review technique (PERT) b) Critical path

Which method for project management removes safety times from task estimates in the planning stage?

a) Program evaluation and review technique (PERT)

b) Critical path method (CPM)

c) Gantt chart

d) Critical chain approach

Step by Step Solution

3.41 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

d Cri... View full answer