Question: Which method for project management removes safety times from task estimates in the planning stage? a) Program evaluation and review technique (PERT) b) Critical path
Which method for project management removes safety times from task estimates in the planning stage?
a) Program evaluation and review technique (PERT)
b) Critical path method (CPM)
c) Gantt chart
d) Critical chain approach
Step by Step Solution
3.41 Rating (157 Votes )
There are 3 Steps involved in it
d Cri... View full answer