Question: Construct the project network comprised of activities A to P that satisfies the following precedence relationships: (a) A, B, and C, the first activities of
Construct the project network comprised of activities A to P that satisfies the following precedence relationships:
(a) A, B, and C, the first activities of the project, can be executed concurrently.
(b) D, E, and F follow A.
(c) I and G follow both B and D.
(d) H follows both C and G.
(e) K and L follow I.
(f) J succeeds both E and H.
(g) M and N succeed F, but cannot start until both E and H are completed.
(h) O succeeds M and I.
(i) P succeeds J, L, and O.
(j) K, N, and P are the terminal activities of the project.