Construct the project network comprised of

Construct the project network comprised of activities A to L with the following precedence relationships: (a) A, B, and C, the first activities of the project, can be executed concurrently. (b) A and B precede D. (c) B precedes E, F, and H. (d) F and C precede G. (e) E and H precede I and J. (f) C, D, F, and I precede K. (g) K precedes L. (h) 1, G, and L are the terminal activities of the project