Question: When estimating task durations for a project plan, you should . a. indicate how much time you will spend on the task b. use a
When estimating task durations for a project plan, you should
.
a. indicate how much time you will spend on the task
b. use a “best case,” or optimistic, estimate of the duration
c. plan to use elapsed time from a task’s start to completion
d. a and c
e. All of the above