Question: 11. Approved corrective actions arc an input to which o(the foUowing processes? A. Validate Scope B. Direct and Man:ige Project Work C. Develop Project Charter
11. Approved corrective actions arc an input to which o(the foUowing processes?
A. Validate Scope B. Direct and Man:ige Project Work C. Develop Project Charter D. Develop Schedule