Question: 15. You know that EAC = 375, PV = 300, AC = 200, and EV = 250. You expect the work of the project to
15. You know that EAC = 375, PV = 300, AC = 200, and EV = 250.
You expect the work of the project to continue as planned. What is the ETC?
A. 300 B. 125 C. 175 D. 50