Question: 16. You expect future project performance to be consistent with the project performance experienced to date for this work component. If BAC = 800, ETC

16. You expect future project performance to be consistent with the project performance experienced to date for this work component.

If BAC = 800, ETC = 275, PV = 300, AC = 200, EV = 250, and CPI = 1.25, what is the EAC?

A. 640 B. 750 C. 600 D. 550