Question: 17. Your project depends on a key deliverable from a vendor you've used several times before with great success. You're counting on the delivery to
17. Your project depends on a key deliverable from a vendor you've used several times before with great success. You're counting on the delivery to arrive on June 1. This is an example of a/an ___________________.
A. Constraint B. Objective C. Assumption D. Requirement