Question: Your project depends on a key deliverable from a vendor youve used several times before with great success. Youre counting on the delivery to arrive

Your project depends on a key deliverable from a vendor you’ve used several times before with great success. You’re counting on the delivery to arrive on June 1.

This is an example of a/an ___________________ .

A. constraint B. objective C. assumption D. requirement