Question: 19. A project manager has assembled the project team. They have identified 56 risks on the project, determined what would trigger the risks, rated them
19. A project manager has assembled the project team. They have identified 56 risks on the project, determined what would trigger the risks, rated them on a risk rating matrix, tested their assumptions, and as>esscd the quality of the data used. The team is continuing to move through the risk management process. What has the project manager forgotten to do?
A. Conduct a simulation.
B. Perform risk mitigation.
C. Determine the overall risk ranking for the project.
D. lnvolve other stakeholders.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
