Question: 19. A project manager has assembled the project team. They have identified 56 risks on the project, determined what would trigger the risks, rated them

19. A project manager has assembled the project team. They have identified 56 risks on the project, determined what would trigger the risks, rated them on a risk rating matrix, tested their assumptions, and as>esscd the quality of the data used. The team is continuing to move through the risk management process. What has the project manager forgotten to do?

A. Conduct a simulation.

B. Perform risk mitigation.

C. Determine the overall risk ranking for the project.

D. lnvolve other stakeholders.