Question: A project manager has assembled the project team. They have identified 56 risks on the project, determined what would trigger the risks, rated them on
A project manager has assembled the project team. They have identified 56 risks on the project, determined what would trigger the risks, rated them on a risk rating matrix, tested their assumptions, and assessed the quality of the data used. The team is continuing to move through the risk management process. What has the project manager forgotten to do? A. Simulation B. Risk mitigation C. Overall risk ranking for the project D. Involve other stakeholders