Question: A project manager has assembled the project team, identified the risks on the project, determined what would trigger the risks, rated them on a risk

A project manager has assembled the project team,
A project manager has assembled the project team, identified the risks on the project, determined what would trigger the risks, rated them on a risk rating matrix, tested their assumptions and assessed the quality of the data used. The team is continuing to move through the risk management process Jwhat has the project manager forgotten to do? Select one: O a. Simulation O b. Involving of other stakeholders O c. Overall risk ranking for the project O d. Risk mitigation Ich