Question: 29. During executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of
29. During executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of the te.un to pl:in how to make the change. This is an example of:
A. Mandgement by obiectivl!!>
B Lick of a change management plan C. Cood team relations D. Lick of a ..:]ear work hreakdown strncturc
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts