Question: 1 2 ) Question ID: 2 5 5 During executing, the project manager determines that a change is needed to material purchased for the project.

12)Question ID: 255During executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of the team to plan how to make the change. This is an example of:A. Management by objectivesB. Good team relationsC.Lack of a clear work breakdown structureD.Lack of a change management plan