Question: During project executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of
During project executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of the team to plan how to make the change. This is an example of A. Management by objectives. B. Lack of a change management plan. C. Good team relations. D. Lack of a clear work breakdown structure.
Step by Step Solution
There are 3 Steps involved in it