Question: 3. If earned value (EV) = 3SO, actual cost (AC) - 400, .md planned alue ( PV) = 325, what ts the cost 'Jnance

3. If earned value (EV) = 3SO, actual cost (AC) - 400, .md planned \ alue ( PV) = 325, what ts the cost

\'Jnance (CV)?

I • '

A. 350 B. -75 C. 400 D. -SO