Question: A dependency requiring that design be completed before manufacturing can start is an example of a(n): A. Discretionary dependency. B. External dependency. C. Mandatory dependency.
A dependency requiring that design be completed before manufacturing can start is an example of a(n):
A. Discretionary dependency.
B. External dependency.
C. Mandatory dependency.
D. Scope dependency.