Question: A dependency requiring that design be completed before manufacturing can start is an example of a ( n ) : Question 1 3 options: A

A dependency requiring that design be completed before manufacturing can start is an example of a(n):
Question 13 options:
A)
External dependency
B)
Scope dependency
C)
Discretionary dependency
D)
Mandatory dependency