Question: A project manager determines that there are 15 communication channels in the project. The number of stakeholders in the project must then be: A. 15


A project manager determines that there are 15 communication channels in the project. The number of stakeholders in the project must then be:

A. 15 stakeholders B. 6 stakeholders C. 8 stakeholders D. 105 stakeholders