Question: A project manager has just finished the risk response plan for a US $387,000 engineering project. Which of the following should he probably do NEXT?
A project manager has just finished the risk response plan for a US $387,000 engineering project. Which of the following should he probably do NEXT? A. Determine the overall risk rating of the project. B. Begin to analyze the risks that show up in the project drawings. C. Add work packages to the project work breakdown structure. D. Hold a project risk reassessment.