Question: A project manager has just finished the risk response plan for a $387,000 engineering project. Which of the following should he probably do next? A.

A project manager has just finished the risk response plan for a $387,000 engineering project. Which of the following should he probably do next? A. Determine the overall risk rating of the project. B. Begin to analyze the risks that show up in the project drawings. C. Add work packages to the project work breakdown structure. D. Hold a project risk review.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management For Small Projects Questions!