Question: A project risk manager distributes anonymous questionnaires to project team members to help identify risks. This is called ___________. A. Game Theory B. The Consensus


A project risk manager distributes anonymous questionnaires to project team members to help identify risks. This is called ___________.

A. Game Theory B. The Consensus Method C. Interviewing D. The Delphi Technique.