Question: A recent earned value analysis shows that your project is 20 percent complete, the CPI is 0.67, and the SPI is 0.87. In this situation,

A recent earned value analysis shows that your project is 20 percent complete, the CPI is 0.67, and the SPI is 0.87. In this situation, you should—

a. Perform additional resource planning, add resources, and use overtime as needed to accomplish the same amount of budgeted work

b. Re-baseline the schedule, then use Monte Carlo analysis

c. Conduct a risk response audit to help control risk

d. Forecast potential deviation of the project at completion from cost and schedule targets

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!