Question: After measuring your project performance you note that your schedule variance is $75,000. What would your BEST course of action be? A: Immediately begin fast
After measuring your project performance you note that your schedule variance is $75,000. What would your BEST course of action be?
A: Immediately begin fast tracking the schedule to catch up time.
B: Ask your project sponsor for extra funds to crash the schedule to catch up time.
C: Congratulate your project team on doing well with the project but also submit the information through the approved change control process so that any updates required can be made to the schedule baseline documents.
D: Do nothing because everything is going well on your project and you are obviously a good project manager.