Question: After measuring your project performance you note that your schedule variance is $75,000. What would your best course of action be? Congratulate your project team
After measuring your project performance you note that your schedule variance is $75,000. What would your best course of action be?
Congratulate your project team on doing well with the project but also submit the information through the approved change control process so that any updates required can be made to the schedule baseline documentsB.Ask your project sponsor for extra funds to crash the schedule to catch up timeC.Immediately begin fast tracking the schedule to catch up timeD.Do nothing as everything is going well on your project and you are obviously a good project manager
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
