Question: An activity not on the critical path is completed in half the scheduled time. What is the impact? A. The critical path is shortened.
An activity not on the critical path is completed in half the scheduled time. What is the impact? ❍ A. The critical path is shortened. ❍ B. The slack in the path containing this activity increases. ❍ C. The total cost for this activity decreases. ❍ D. Resources from this activity can be assigned to other activities.