Question: Consider the data in the table below. Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means
Consider the data in the table below. Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means you are calculating your EAC by using which of the following formulas?
Activity
% Complete PV EV AC A
100 2,000 2,000 2,200 B
50 1,000 500 700 C
0 1,000 0
0
a. EAC = AC/EV × BAC
b. EAC = AC/EV × [work completed and in progress] + [actual (or revised) cost of work packages that have not started]
c. EAC = [Actual to date] + [all remaining work to be done at the planned cost including remaining work in progress]
d. EAC =% complete × BAC
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
