Question: Consider the data in the table below. Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means

Consider the data in the table below. Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means you are calculating your EAC by using which of the following formulas?

Activity

% Complete PV EV AC A

100 2,000 2,000 2,200 B

50 1,000 500 700 C

0 1,000 0

0

a. EAC = AC/EV × BAC

b. EAC = AC/EV × [work completed and in progress] + [actual (or revised) cost of work packages that have not started]

c. EAC = [Actual to date] + [all remaining work to be done at the planned cost including remaining work in progress]

d. EAC =% complete × BAC

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!