Question: Consider the data in the table below. Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means
Consider the data in the table below. Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means you are calculating your EAC by using which of the following formulas?
a. EAC = AC/EV × BAC
b. EAC = AC/EV × [work completed and in progress] + [actual or revised cost of work packages that have not started]
c. EAC = AC + Bottom-up ETC
d. EAC = % complete × BAC
Activity % Complete PV EV AC A 100 2,000 2,000 2,200 B 50 1,000 500 700 C 0 1,000 0 0