Question: During the Identify Risks process, a project manager made a long list of risks identified by all the stakeholders using various methods. He then made
During the Identify Risks process, a project manager made a long list of risks identified by all the stakeholders using various methods. He then made sure that all the risks were understood and that triggers had been identified. Later, in the Plan Risk Responses process, he took all the risks identified by the stakeholders and determined ways to mitigate them. What has he done wrong? A. The project manager should have waited until the Perform Qualitative Risk Analysis process to get the stakeholders involved. B. More people should be involved in the Plan Risk Responses process. C. The project manager should have created workarounds. D. Triggers are not identified until the Identify Risks process.