Question: During the Identify Risks process, a project manager and stakeholders used various methods to identify risks and created a long list of those risks. The
During the Identify Risks process, a project manager and stakeholders used various methods to identify risks and created a long list of those risks. The project manager then made sure all the risks were understood and that triggers had been identified. Later, in the Plan Risk Responses process, he took all the risks identified by the stakeholders and determined ways to mitigate them. What has he done wrong? A. The project manager should have waited until the Perform Qualitative Risk Analysis process to get the stakeholders involved. B. More people should have been involved in the Plan Risk Responses process. C. The project manager should have created workarounds. D. Triggers should not be identified until the Implement Risk Responses process.