Question: During the project execution, a stakeholder comes to you and tells you that she suspects that some team members are not doing their tasks and
During the project execution, a stakeholder comes to you and tells you that she suspects that some team members are not doing their tasks and are busy with other activities. You discuss her concerns with her and show her a document. After seeing it, she agrees with that the team members are doing the right job. What document was this?
(a) RACI chart
(b) GANTT chart
(c) Organizational chart
(d) WBS Go to the Answer