Question: During your cost estimating you include a figure for cost uncertainty on your project, and the project sponsor agrees to give you delegated authority to
During your cost estimating you include a figure for cost uncertainty on your project, and the project sponsor agrees to give you delegated authority to manage this reserve. What is this figure generally known as?
A: Reserve analysis B: Contingency reserve C: Management reserve D: Slush fund