Question: While completing the cost estimating for a particular activity in your project, several members of your team disagree over the estimate to do the work.

While completing the cost estimating for a particular activity in your project, several members of your team disagree over the estimate to do the work. After a discussion with the team, you determine that the most likely cost of the activity will be

$50, the optimistic cost of the activity will be $30, and the pessimistic cost will be $70.

Using the three-point estimating technique, what is the expected cost of the activity?

A: $150 B: $25 C: $70 D: $50

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!