Question: You are using the three-point estimating method of scheduling for a project. The variance for the project is found to be 16 days and the

You are using the three-point estimating method of scheduling for a project. The variance for the project is found to be 16 days and the duration of the project is found to be 90 days. What is the range of values for the project duration such that there will be at least a 95% probability that the actual project completion will fall between the high and low value of the range of values?

A: 58-122 days B: 74-106 days C: 82-98 days D: 86-94 days