Question: Given: BAC = 200 ACC = 120 EV = 80 CPI = 0.666 Assuming that current variances are typical of future variances, the estimate at
Given: BAC = 200 ACC = 120 EV = 80 CPI = 0.666 Assuming that current variances are typical of future variances, the estimate at completion (EAC) is: A. 220.