Question: Given: BAC 200 ACC = 120 EV = 80 CPI = 0.666 Assuming that current variances are atypical, and that similar variances will not occur
Given: BAC 200 ACC = 120 EV = 80 CPI = 0.666 Assuming that current variances are atypical, and that similar variances will not occur in the future, the estimate at completion (EAC) is: A. 120.
B. 160.
C. 200.
D. 240.