Question: How would you calculate your EAC if the ETC work will be performed at the budgeted rate? A. EAC = BAC/CPI B. EAC= BAC-EV C.


How would you calculate your EAC if the ETC work will be performed at the budgeted rate?

A. EAC = BAC/CPI B. EAC= BAC-EV C. EAC = AC + BAC - EV D. EAC=(BAC-EV)*CPI