Question: How would you calculate your EAC if the ETC work is performed at the budgeted rate? EAC = BAC/CPI EAC= BAC-EV EAC = AC +
How would you calculate your EAC if the ETC work is performed at the budgeted rate?
EAC = BAC/CPI EAC= BAC-EV EAC = AC + BAC - EV EAC=(BAC-EV)*CPI