Question: If a successor activity cannot start until its predecessor activity has started, what sort of relationship is this? A. Finish-to-start B. Start-to-start C. Finish-to-finish D.

If a successor activity cannot start until its predecessor activity has started, what sort of relationship is this?

A. Finish-to-start B. Start-to-start C. Finish-to-finish D. Start-to-finish