Question: The precedence diagramming method ( PDM ) is a technique used for constructing a schedule model in which activities are represented by nodes, and are
The precedence diagramming method PDM is a technique used for constructing a schedule model in which activities are represented by nodes, and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed. PDM includes four types of dependencies or logical relationships.
Match the concept to its appropriate definition.
Question options:
A logical relationship in which a successor activity cannot start until a predecessor activity has started. For example, level concrete successor cannot begin until pour foundation predecessor begins.
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished. For example, writing a document predecessor is required to finish before editing the document successor can finish.
A logical relationship in which a predecessor activity cannot finish until a successor activity has started. For example, a new accounts payable system successor has to start before the old accounts payable system can be shut down predecessor
A logical relationship in which a successor activity cannot start until a predecessor activity has finished. For example, installing the operating system on a PC successor cannot start until the PC hardware is assembled predecessor
Finishtostart FS
Finishtofinish FF
Starttostart SS
Starttofinish SF
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock