Question: Pair the concept with its correct definition or statement. Start-to-Start (SS) Sequence Activities Crashing Resource Smoothing Lag Group B A logical relationship in which a
Pair the concept with its correct definition or statement.
Start-to-Start (SS)
Sequence Activities
Crashing
Resource Smoothing
Lag
Group B
A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Only for activities on the critical path where additional resources will shorten the activitys duration.
Projects critical path is not changed and the completion date may not be delayed.
The process of identifying and documenting relationships among the project activities.
Amount of time a successor activity will be delayed with respect to a predecessor activity.