Question: If Task C starts two days late, what is the effect on the project end date? A. The project ends one day late because
If Task C starts two days late, what is the effect on the project end date? ❍ A. The project ends one day late because there is slack of one day. ❍ B. The project is still two days early because Tasks B, D, and F each have one day of slack. ❍ C. The project is one day late because Task C is on the critical path. ❍ D. There is no effect on the project end date.