Question: When developing the estimates for project phases, you choose to add the individual estimates for the activities that comprise each phase. What type of estimation
When developing the estimates for project phases, you choose to add the individual estimates for the activities that comprise each phase. What type of estimation method are you using? ❍ A. Parametric estimating ❍ B. Bottom-up estimating ❍ C. Top-down estimating ❍ D. Analogous estimating