Question: If, when developing your project schedule, you want to define a distribution of probable results for each schedule activity and use that distribution to calculate
If, when developing your project schedule, you want to define a distribution of probable results for each schedule activity and use that distribution to calculate another distribution of probable results for the total project, the most common technique to use is—
a. What-if scenario analysis
b. Monte Carlo analysis
c. Linear programming
d. Concurrent engineering