Question: If, when developing your project schedule, you want to define a distribution of probable results for each schedule activity and use that distribution to calculate
If, when developing your project schedule, you want to define a distribution of probable results for each schedule activity and use that distribution to calculate another distribution of probable results for the total project, the most common technique to use is-
A. What-if scenario analysis B. * Monte Carlo analysis C. Linear programming D. Concurrent engineering