Question: In the earned value technique, cost variance is computed as: A. EV minus PV. B. EV minus AC. C. AC minus EV. D. PV minus

In the earned value technique, cost variance is computed as: A. EV minus PV. B. EV minus AC. C. AC minus EV. D. PV minus EV.