Question: In Earned Value Management, Cost Variance ( CV ) is equal to: Group of answer choices EV minus PV AC minus EV EV minus AC

In Earned Value Management, Cost Variance (CV) is equal to:
Group of answer choices
EV minus PV
AC minus EV
EV minus AC
PV minus EV