Question: Project schedule development is an iterative process. If the start and finish dates are not realistic, the project probably will not finish as planned. You

Project schedule development is an iterative process. If the start and finish dates are not realistic, the project probably will not finish as planned. You are working with your team to define how to manage schedule changes. You documented your decisions in which of the following?

a. Schedule change control procedures

b. Schedule management plan

c. Schedule risk plan

d. Service-level agreement

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!