Question: Rolling wave planning in the Create WBS process refers to situations in which a. Certain deliverables or subprojects will be accomplished far into the future

Rolling wave planning in the Create WBS process refers to situations in which—

a. Certain deliverables or subprojects will be accomplished far into the future

b. Additional work is added to the project after the scope baseline has been established; therefore, additional decomposition is required

c. Identification codes for the WBS elements cannot be determined until the schedule activity list is complete in case revisions are required

d. Subprojects are developed by external organizations and then become part of the WBS for the entire project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!